Improvement v Premises: Northern Bulk Draws the Line
Key Takeaway
The recent decision of 1499545 Ontario Inc. (Northern Bulk Logistics) v Construction Energie Renouvelable GP/S.E.N.C., 2025 ONSC 111, considered whether the claim for lien of Northern Bulk Logistics (“Northern Bulk“) and the lien of another lien claimant (i.e., Corbiere) related to the same premises. The crux of the issue argued before the court was that if both liens related to the same premises, then Northern Bulk had to be served with a notice of trial in the Corbiere action and therefore became a party to that action. If Northern Bulk was a party to that action, then Northern Bulk’s lien could be enforced as part of the Corbiere action.
The Court held that the improvement that gives rise to the lien is restricted to the improvement on the lands described in the claim for lien. In this case, the Court concluded that the lands subject to the Northern Bulk’s lien were entirely different than the lands subject to the Corbiere land. Therefore, Northern Bulk’s plaintiff’s lien could not be enforced in the Corbiere action because the two lien actions did not relate to the same premises.
Notably, the Superior Court of Justice’s decision is under appeal. It remains to be seen whether the appellate court will uphold the lower court’s reasoning or adopt a different approach. Regardless, what is clear is that it is critical to ensure that your lien or your client’s claim is set down or an order for trial is obtained within the two-year period stipulated under the Construction Act.
Factual Context
In this case, the issue before the court concerned two streams of contracting parties for the development of a wind-powered electric generating facility (the “Project“).
The first stream of contracting parties fell under Construction Energie Renouvelable GP/S.E.N.C. (“CER“). In brief:
-
- CER was the general contractor for the construction of the wind turbines.
- CER subcontracted with TimberRidge to provide road maintenance services.
- TimberRidge subcontracted with Northern Bulk.
- On October 23, 2019, Northern Bulk registered its lien which was subsequently perfected on December 3, 2019.
- At the two-year anniversary of the issuance of the statement of claim, Northern Bulk had not set down its action for trial and had not obtained a trial date.
The second stream of contracting parties fell under PowerTel Utilities. In brief:
-
- PowerTel Utilities Contractors Limited was the general contractor for the construction of the transmission lines.
- Corbiere was a subcontractor to PowerTel.
- Corbiere registered a claim for lien on September 6, 2019 which was subsequently perfected on October 17, 2019.
- The Corbiere action was set down for trial on March 19, 2021.